Cross Lanes Widening

Project Updates

NEW TRAFFIC PATTERN

9/4/2025
The Cross Lanes Widening Project has resumed construction.  Work is being performed in  the areas that are currently coned off from the Kroger intersection to WV 62 intersection. 

NEW TRAFFIC PATTERN BEGINING 9/10/2025 8:00 PM.

PHASE 2 TRAFFIC CONTROL

Temporary Traffic Control Phase (2) will be in place beginning 9/10/2025 8:00 PM – WV 622 partial lane closure northbound beginning at I-64 West Bound Exit Ramp to Cadel Drive (CR 622/28) and transitioning to the intersection of WV 62 (Cross Lanes Dr / Washington St. W) with existing Phases (13) and (10) traffic control remaining in place. Northbound traffic moved to the center turn lane with a lane shift. Temporary traffic control signage, cones, and roadway striping will define new traffic pattern. Digital message boards are in place, denoting new traffic patterns ahead.

Traffic will remain in the current state until the completion of phases 2, 10  and 13. The traveling public is asked to travel the Work Zone Speed Limit of 25 MPH while traveling through the area. Caution should be taken when exiting and entering driveways and area businesses. Traffic is asked to not block intersections and entrances when possible.

WVDOH Website, CLICK HERE:
WVDOH Cross Lanes project link with original traffic visualizations

Cross Lanes Widening

Latest News

Important project updates and announcements, and related local media stories.

New Traffic Pattern 9/10/2025

Temporary Traffic Control Phase (2) will be in place beginning 9/10/2025 8:00 PM – WV 622 partial lane closure northbound beginning at I-64 West Bound Exit Ramp to Cadel Drive …

Project Update

July 28, 2025The Cross Lanes Widening Project is scheduled to resume construction beginning August 4, 2025.  Work will resume in the areas that are currently coned off from the Kroger …

April 02, 2025 Project Update

A few utilities remain throughout the project that still need to be relocated to allow contract work to proceed. Work on the project will be significantly minimized during the utility …

Update – Utilities

Various utilities throughout the project need to be relocated to allow contract work to proceed. Work on the project will be significantly minimized during the utility relocation efforts. The project …

New Phase of Construction

New Traffic Pattern!New Phase of Project has Begun.In the early A.M. hours of 6/14/2024 the Cross Lanes widening project made its second traffic switch for the phased construction.The current phase …

!!! Important Update !!!

Change in Start of New Traffic Pattern Reason For Change: The upcoming change in traffic pattern has been delayed, due to additional unforeseen work that requires additional time to perform.  …

Project Update – 05/13/2024

Notice of Traffic Pattern Change Location: WV 622 Big Tyler Road, Cross Lanes WV Scheduled Lane Shift: Beginning 5/15/2024, pending weather Description of Change: Due to the current construction along …

Weekly Update – 11/13/23

No Change in Traffic patterns for the upcoming week beginning 11/13/2023. Daily road closures along Sun Valley Drive to through traffic only from 9:00 AM to 3:00 PM.  Access to …