!!! Important Update !!!
Change in Start of New Traffic Pattern Reason For Change: The upcoming change in traffic pattern has been delayed, due to additional unforeseen work that requires additional time to perform. …
The WV 622 – Cross Lanes Widening project will widen WV 622 from Goff Mountain Road to the intersection with WV 62 and on towards Andrew Jackson Middle School.
The project’s goals are to reduce traffic congestion, increase safety, and enhance stormwater management.
!!! Important Update: !!!
Change in Start of New Traffic Pattern
Reason For Change:
The upcoming change in traffic pattern has been delayed, due to additional unforeseen work that requires additional time to perform. This additional work will allow the new traffic pattern to be implemented with smoother transitions and traffic flow through the affected areas. Once the new traffic pattern is placed it will remain until completed.
**The message boards throughout the project have been changed and will be updated within 7 days of the traffic control change.
**Additional information will be sent out and updated on the project website.
The project will continue to have multiple Sub-Contractors on site working on various construction items behind installed temporary barriers. Work will include excavation of existing roadway, sidewalks and areas for planned retaining walls. This work will be on-going. The placement of the new high mast lighting foundations around the Cross Lanes exit is included in this project.
Phase 1: Gatewater Rd. STA 4000+00 – STA 4014+07 LT & RTConstruction: Sidewalk, Curb, Pavement, Drainage Improvements, Entrance to City Bank and County Lot. Phase 2: WV 622 Northbound STA 29+45 …
Phase 11: Washington Street and Sun Valley Drive Construction: Drainage Improvements
Phase 12: WV 622 Northbound STA 57+50 – STA 82+45 RTTraffic Control: Case A13 (MUTCD Typical Application 34)Construct: Retaining Walls 6 & 7, Sidewalk, Curb, Pavement, and Drainage Improvements. Phase 13: …
Phase 14: WV 622 STA 57+50 – STA 81+45 CenterlineConstruct: Pavement, and Drainage Improvements.
The project began in mid-August 2023.
The projected completion date for the project is June 2025. Approximately 22 Months.
No, the design does not include any roundabouts.
Day and Night shifts will be utilized. The contractor will be required to work shifts that have the least amount of impact to the traveling public based of the phase of work being performed at the time.
During construction there will be multiple lane changes and switching of traffic patterns. Lane closures and shifts are necessary to perform all phases of construction. During construction north and south traffic will flow through a guided work zone with work zone construction signs, cones, barrels, and barricades to aid in directing flow of traffic. Some closures will be between the hours of 9:00 AM to 3:00 PM. The work zone speed limit will be 25 MPH.
Pedestrian traffic will be affected during certain stages of construction. During this time alternative routes may be required through the work zone with special attention to safety, However the contractor will be required to maintain access to all houses, schools, and businesses at all times.
The Contractor will notify businesses of updates to changing phases of traffic control in a specific location. The contractor will be required to maintain access at all times.
Please expect delays throughout the time frame of the project. Delays will be based on the current phase, location, and type of construction being performed daily. Delays are anticipated to be in early AM commute hours, Mid-Day hours, and PM commute hours.
Please do not block driveways and intersections.
Follow the project website: crosslaneswidening.com
Email: info@crosslaneswidening.com and ask to receive the weekly project update emails.
Some phases of work will be performed at night. This gives the perception the contractor is not working during the day. However, work is being performed at night in lieu of normal day time hours.
Currently, the project is under construction with some work beginning as early as August and September to move or relocate utilities. Construction on Sun Valley Drive and on WV 622 recently began. The project is proceeding on schedule.
These Apps can provide phone notifications of safety issues and traffic information in Kanawha County. Some include Public Notification System Opt-Ins.
Notifications in traffic pattern changes will be made via the digital message boards and the media.
Important project updates and announcements, and related local media stories.
Change in Start of New Traffic Pattern Reason For Change: The upcoming change in traffic pattern has been delayed, due to additional unforeseen work that requires additional time to perform. …
Notice of Traffic Pattern Change Location: WV 622 Big Tyler Road, Cross Lanes WV Scheduled Lane Shift: Beginning 5/15/2024, pending weather Description of Change: Due to the current construction along …
No Change in Traffic patterns for the upcoming week beginning 11/13/2023. Daily road closures along Sun Valley Drive to through traffic only from 9:00 AM to 3:00 PM. Access to …
No Change in Traffic patterns for the upcoming week beginning 11/06/2023. Construction is being performed on WV 622 North, beginning past the intersection of Cross Lanes Drive and Washington Street …
No Change in Traffic patterns for the upcoming week beginning 10/30/2023. Construction is being performed on WV 622 North, beginning past the intersection of Cross Lanes Drive and Washington Street …
No Change in Traffic patterns for the upcoming week beginning 10/23/2023. Construction is being performed on WV 622 North, beginning past the intersection of Cross Lanes Drive and Washington Street …
No Change in Traffic patterns for the upcoming week beginning 10/16/2023. Construction is being performed on WV 622 North, beginning past the intersection of Cross Lanes Drive and Washington Street …
Prime Contractor Triton Construction is scheduled to begin placing temporary barrier along WV 622 North, with no change to current traffic pattern. Contractor will continue placing elliptical pipe and manholes …
A project widening WV 622 through the most congested part of Cross Lanes is among 34 projects included in a bid letting conducted by the West Virginia Division of Highways …